Activity: Create Baselines
Purpose
- To ensure that all developed artifacts are captured and archived,
at given points in time, as a basis for further product development.
|
Role:
Integrator
|
Frequency: Ongoing |
Input Artifacts:
|
Resulting Artifacts:
|
Good candidates for a baseline are the sets of files and directories under
version control that are developed, integrated and released together. A baseline
identifies one and only one version of a element. Composite baselines
are groupings of baselines delivered by teams working on separate subsystems
of the overall project.
Part of the iterative development methodology is to constantly build an
executable product. A baseline should be seen as the moving front of development
which contains the necessary artifacts for subsequent development. So baselines
should be created certainly at the end of each iteration.
Project baselining practices are followed in accordance with the
configuration identification, baselining and archiving step defined in Activity:
Establish CM Policies.
|