Tool Mentor: Creating a Baseline of a Rational RequisitePro Project
Purpose
This tool mentor describes how to create a baseline of requirements
using Rational Administrator® and Rational ClearCase®.
This section provides links to additional information related to this tool mentor.
Overview
It is a good idea to create a baseline of a requirements project at each
project milestone.
A baseline creates a ClearCase object that represents a stable
configuration of the Rational RequisitePro® project at a particular time. This
object can be used to create a new project.
A RequisitePro project consists of a requirements database, project views,
and documents containing requirements. Requirements can be created either
directly in a project view or in a Microsoft® Word document in RequisitePro.
All requirements are stored in the database, regardless of their location within
the project. You can create a baseline of any RequisitePro project, regardless
of whether it uses an Oracle, Microsoft Access, or SQL Server database.
Note: For information on archiving a RequisitePro project,
see Tool Mentor: Archiving Requirements
Using RequisitePro.
Create a project baseline with Unified Change Management ![To top of page](../../images/top.gif)
Using the Unified Change Management (UCM) model, RequisitePro project
administrators can create baselines of RequisitePro projects by performing tasks
in Rational Administrator and ClearCase.
Before you create a baseline of a RequisitePro project, you must first meet the
following preconditions:
- The RequisitePro project must be associated with a UCM-enabled Rational
project in Rational Administrator.
- The RequisitePro project must be closed, with no active users.
To create a baseline of a RequisitePro project:
- Open the Rational Administrator.
- Right-click the Administrator project and click Configure.
- In the Configure Project dialog box in the Requirement Assets area, click Check In All.
- At the messages that follow, confirm your selection and type an activity
to describe the baseline.
- After the Check In All operation is completed, close the Configure Project
dialog box.
- In the Rational Administrator Tools menu, click Rational
ClearCase Project Explorer. The ClearCase Explorer appears.
- Right-click the RequisitePro Requirements Assets integration stream and click Make Baseline in the shortcut menu.
- Type a baseline title, select Full for the baseline type,
select a View Context, and click OK.
For More Information
Refer to the topic Creating
baselines with Unified Change Management (Index: creating>baselines)
in the RequisitePro online Help.
|