Tool Mentor: Creating a Baseline of a Rational RequisitePro Project
Purpose
This tool mentor describes how to create a baseline of requirements
using Rational Administrator® and Rational ClearCase®.
This section provides links to additional information related to this tool mentor.
Overview
It is a good idea to create a baseline of a requirements project at each
project milestone.
A baseline creates a ClearCase object that represents a stable
configuration of the Rational RequisitePro® project at a particular time. This
object can be used to create a new project.
A RequisitePro project consists of a requirements database, project views,
and documents containing requirements. Requirements can be created either
directly in a project view or in a Microsoft® Word document in RequisitePro.
All requirements are stored in the database, regardless of their location within
the project. You can create a baseline of any RequisitePro project, regardless
of whether it uses an Oracle, Microsoft Access, or SQL Server database.
Note: For information on archiving a RequisitePro project,
see Tool Mentor: Archiving Requirements
Using RequisitePro.
Create a project baseline with Unified Change Management
Using the Unified Change Management (UCM) model, RequisitePro project
administrators can create baselines of RequisitePro projects by performing tasks
in Rational Administrator and ClearCase.
Before you create a baseline of a RequisitePro project, you must first meet the
following preconditions:
- The RequisitePro project must be associated with a UCM-enabled Rational
project in Rational Administrator.
- The RequisitePro project must be closed, with no active users.
To create a baseline of a RequisitePro project:
- Open the Rational Administrator.
- Right-click the Administrator project and click Configure.
- In the Configure Project dialog box in the Requirement Assets area, click Check In All.
- At the messages that follow, confirm your selection and type an activity
to describe the baseline.
- After the Check In All operation is completed, close the Configure Project
dialog box.
- In the Rational Administrator Tools menu, click Rational
ClearCase Project Explorer. The ClearCase Explorer appears.
- Right-click the RequisitePro Requirements Assets integration stream and click Make Baseline in the shortcut menu.
- Type a baseline title, select Full for the baseline type,
select a View Context, and click OK.
For More Information
Refer to the topic Creating
baselines with Unified Change Management (Index: creating>baselines)
in the RequisitePro online Help.
|