Online Collegiate Paging Service Iteration Plan
Version 3.0
Revision History
Table of ContentsIteration Plan Introduction
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Task |
Start |
End |
| Construction Kick-off | Mon 11/29/99 | Tue 11/30/99 |
| Bring Full development team on board | Mon 11/29/99 | Mon 11/29/99 |
| Bring Full Testing staff on board | Mon 11/29/99 | Mon 11/29/99 |
| Construction Kick-off Meeting | Mon 11/29/99 | Tue 11/30/99 |
| Prepare for construction kick-off meeting | Mon 11/29/99 | Mon 11/29/99 |
| Hold Construction Kick-off Meeting | Mon 11/29/99 | Tue 11/30/99 |
| Celebrate project construction start w/entire team | Tue 11/30/99 | Tue 11/30/99 |
| Construction Kick-off Completed | Tue 11/30/99 | Tue 11/30/99 |
| First iteration | Tue 11/30/99 | Thu 12/16/99 |
| Do Technical Reviews | Tue 11/30/99 | Tue 11/30/99 |
| Technical Reviews 1 | Tue 11/30/99 | Tue 11/30/99 |
| Technical Reviews 2 | Tue 11/30/99 | Tue 11/30/99 |
| Test Planning | Tue 11/30/99 | Tue 11/30/99 |
| Software test plan for next iteration created, reviewed, and signed off | Tue 11/30/99 | Tue 11/30/99 |
| Software test cases for next iteration created, reviewed and signed off' | Tue 11/30/99 | Tue 11/30/99 |
| Software test plan and test cases for current iteration updated | Tue 11/30/99 | Tue 11/30/99 |
| Iteration Planning | Tue 11/30/99 | Tue 11/30/99 |
| Integration Build Plan created, reviewed, and signed off | Tue 11/30/99 | Tue 11/30/99 |
| Detailed Software Construction Plan for current interation including miniature milestones created, reviewed, and signed off | Tue 11/30/99 | Tue 11/30/99 |
| Update test plan, focusing on this iteration | Tue 11/30/99 | Tue 11/30/99 |
| Refine test cases for this iteration | Tue 11/30/99 | Tue 11/30/99 |
| Create test environment | Tue 11/30/99 | Tue 11/30/99 |
| Create software build instructions (make files) for current iteration | Tue 11/30/99 | Tue 11/30/99 |
| Beginning-of-iteration planning completed | Tue 11/30/99 | Tue 11/30/99 |
| Develop First Iteration | Tue 11/30/99 | Thu 12/16/99 |
| Code & Test Use Case Approve Story | Tue 11/30/99 | Wed 12/8/99 |
| Do Detailed Design | Tue 11/30/99 | Wed 12/1/99 |
| Review & Refine Architecture Design | Wed 12/1/99 | Wed 12/1/99 |
| Review & Refine Database Design | Wed 12/1/99 | Thu 12/2/99 |
| Develop Code or Modify Generated Code (if applicable) | Thu 12/2/99 | Fri 12/3/99 |
| Research and Resolve Development Tool Bugs (if applicable) | Fri 12/3/99 | Tue 12/7/99 |
| Conduct Code Review | Tue 12/7/99 | Tue 12/7/99 |
| Unit Testing | Tue 12/7/99 | Wed 12/8/99 |
| Add code to configuration management | Wed 12/8/99 | Wed 12/8/99 |
| Code & Test Use Case Edit Profile | Tue 11/30/99 | Wed 12/8/99 |
| Do Detailed Design | Tue 11/30/99 | Wed 12/1/99 |
| Review & Refine Architecture Design | Wed 12/1/99 | Wed 12/1/99 |
| Review & Refine Database Design | Wed 12/1/99 | Thu 12/2/99 |
| Develop Code or Modify Generated Code (if applicable) | Fri 12/3/99 | Tue 12/7/99 |
| Research and Resolve Development Tool Bugs (if applicable) | Tue 12/7/99 | Tue 12/7/99 |
| Conduct Code Review | Tue 12/7/99 | Tue 12/7/99 |
| Unit Testing | Wed 12/8/99 | Wed 12/8/99 |
| Add code to configuration management | Wed 12/8/99 | Wed 12/8/99 |
| Code & Test Use Case Send Page | Tue 11/30/99 | Thu 12/16/99 |
| Do Detailed Design | Tue 11/30/99 | Thu 12/2/99 |
| Review & Refine Architecture Design | Thu 12/2/99 | Thu 12/2/99 |
| Review & Refine Database Design | Thu 12/2/99 | Thu 12/2/99 |
| Develop Code or Modify Generated Code (if applicable) | Thu 12/9/99 | Fri 12/10/99 |
| Research and Resolve Development Tool Bugs (if applicable) | Fri 12/10/99 | Tue 12/14/99 |
| Conduct Code Review | Tue 12/14/99 | Wed 12/15/99 |
| Unit Testing | Wed 12/15/99 | Wed 12/15/99 |
| Add code to configuration management | Thu 12/16/99 | Thu 12/16/99 |
| Code & Test Use Case Read Content on Website | Tue 11/30/99 | Thu 12/16/99 |
| Do Detailed Design | Tue 11/30/99 | Thu 12/2/99 |
| Review & Refine Architecture Design | Thu 12/2/99 | Thu 12/2/99 |
| Review & Refine Database Design | Thu 12/2/99 | Thu 12/2/99 |
| Develop Code or Modify Generated Code (if applicable) | Fri 12/10/99 | Tue 12/14/99 |
| Research and Resolve Development Tool Bugs (if applicable) | Tue 12/14/99 | Wed 12/15/99 |
| Conduct Code Review | Wed 12/15/99 | Wed 12/15/99 |
| Unit Testing | Wed 12/15/99 | Thu 12/16/99 |
| Add code to configuration management | Thu 12/16/99 | Thu 12/16/99 |
| First Iteration Developed | Thu 12/16/99 | Thu 12/16/99 |
| Integration Testing | Wed 12/8/99 | Fri 12/10/99 |
| Integration with system | Wed 12/8/99 | Thu 12/9/99 |
| Conduct Integration Test | Thu 12/9/99 | Thu 12/9/99 |
| Document Problems | Thu 12/9/99 | Thu 12/9/99 |
| Modify Code As Applicable | Thu 12/9/99 | Fri 12/10/99 |
| Conduct Regression Test | Fri 12/10/99 | Fri 12/10/99 |
| Obtain Sign-off | Fri 12/10/99 | Fri 12/10/99 |
| Integration Test Complete | Fri 12/10/99 | Fri 12/10/99 |
| Installation | Fri 12/10/99 | Mon 12/13/99 |
| Install program created, reviewed, and signed off | Fri 12/10/99 | Fri 12/10/99 |
| Install Software for User Acceptance Testing | Fri 12/10/99 | Fri 12/10/99 |
| User Manual/Specification/Help updated | Fri 12/10/99 | Mon 12/13/99 |
| Training Materials updated (if applicable) | Mon 12/13/99 | Mon 12/13/99 |
| Obtain Sign-off | Mon 12/13/99 | Mon 12/13/99 |
| Installation Complete | Mon 12/13/99 | Mon 12/13/99 |
| User Checkpoint | Mon 12/13/99 | Mon 12/13/99 |
| Prepare for User Checkpoint | Mon 12/13/99 | Mon 12/13/99 |
| User Checkpoint Meeting and Demonstration | Mon 12/13/99 | Mon 12/13/99 |
| Have team, including client project manager, complete the work release sign-off form | Mon 12/13/99 | Mon 12/13/99 |
| First iteration code complete | Mon 12/13/99 | Mon 12/13/99 |
| User Acceptance Testing | Mon 12/13/99 | Tue 12/14/99 |
| Initiate User acceptance testing | Mon 12/13/99 | Tue 12/14/99 |
| Prepare for User sign-off meeting | Tue 12/14/99 | Tue 12/14/99 |
| Have team, including client project manager, complete the work release sign-off form | Tue 12/14/99 | Tue 12/14/99 |
| First Iteration User Acceptance Test Complete | Tue 12/14/99 | Tue 12/14/99 |
| Wrap-up First Iteration | Tue 12/14/99 | Thu 12/16/99 |
| Conduct Quality Check Meeting with Client | Tue 12/14/99 | Tue 12/14/99 |
| Hold Client Business-focused Lessons Learned Meeting | Tue 12/14/99 | Tue 12/14/99 |
| Hold Client Technical-focused Lessons Learned Meeting | Tue 12/14/99 | Tue 12/14/99 |
| Hold Context Lessons Learned Meeting | Tue 12/14/99 | Wed 12/15/99 |
| Iterative Delivery Project Plan updated, reviewed, and signed off | Wed 12/15/99 | Wed 12/15/99 |
| Software Development Plan updated, reviewed, and signed off | Wed 12/15/99 | Wed 12/15/99 |
| Knowledge Transfer Plan updated, reviewed, and signed off | Wed 12/15/99 | Wed 12/15/99 |
| Project estimates updated (accurate to +30%, -20%) | Wed 12/15/99 | Wed 12/15/99 |
| Move appropriate deliverables from Project Homepage to IAN Artifacts | Wed 12/15/99 | Thu 12/16/99 |
| First Iteration Wrap-up Completed | Thu 12/16/99 | Thu 12/16/99 |
The following deliverables or artifacts will be generated and reviewed during the first Construction Iteration:
| Artifact Set | Deliverable | Responsible Owner | |
| Design Set | Implementation Model | Ken Perch | |
| Implementation Set | Integration Build Plan
Test Drivers, Stubs, Data, & Scripts Test Procedures Test Evaluation Report Components |
Mary Durham
Mike Hunziker Chris Curvey Mary Durham Justin Woddis |
|
| Management Set | Iteration Plan
Project Plan (update) Project Schedule (update) Project Risk List (update) Status Assessment Iteration Assessment Test Plan |
Mary Durham
Mary Durham Mary Durham Mary Durham Mary Durham Mary Durham Mary Durham |
|
The project staffing for this iteration can be viewed as follows:

The budget for this iteration is $150,000. WebNewsOnLine has secured this funding.
Use cases to be implemented during this iteration are: