Risk
Ranking/ Magnitude |
Risk Description
& Impact |
Mitigation
Strategy and/or Contingency Plan |
8 |
Volume of students logged on during peak hours of the registration
period may significantly degrade system performance.
|
Further develop prototype to obtain more accurate numbers.
|
7 |
R1 and R2 Releases may slip and not be available by September 1999 -
the start of the Registration Period.
|
Monitor progress against the schedule & milestones.
Update effort to complete and time to complete on a regular basis.
|
5 |
Interfaces to the old legacy Billing and Course Catalog Systems may
introduce performance and response time issues.
|
Continue to develop prototype. Monitor this issue at weekly progress
meetings.
|
4 |
One Developer position remains unfilled. If not filled by the start of
the Construction Phase, the schedule could slip by up to 5 weeks.
|
Contact local recruiting agencies. Action: Rick Bell.
|
3 |
Strike Action of College Facility Union Workers may impact project
schedule if IT services are unavailable.
|
Monitor.
|